GC - Larry's Creek Water Treatment Plant

Project Files

  • Addenda
    • Addendum 1 Uploaded: 12/9/2024 (11137 kb)
    • Addendum 2.pdf Uploaded: 12/13/2024 (289 kb)
    • Addendum 3.pdf Uploaded: 12/24/2024 (2761 kb)
  • Addenda Drawings
    • Addn 1
      • E06 Site Pl Conduit Sch Addn 1 Uploaded: 12/9/2024 (335 kb)
      • E09 Process AreaElec Rm Pwr Pl Addn 1 Uploaded: 12/9/2024 (1219 kb)
      • E10 Chem FdStrg Rm-RestrmJanitor Closet Pwr Pl Addn 1 Uploaded: 12/9/2024 (543 kb)
      • E16 OA WTP Sec Pl Addn 1 Uploaded: 12/9/2024 (1157 kb)
      • E17 Raw Wtr Chem Fd Bldg Pwr Pl Addn 1 Uploaded: 12/9/2024 (533 kb)
      • E24 Pnl Schs Addn 1 Uploaded: 12/9/2024 (387 kb)
      • E25 Lgt Fixture SchDtls Addn 1 Uploaded: 12/9/2024 (650 kb)
      • E26 Dtls Addn 1 Uploaded: 12/9/2024 (529 kb)
      • E31 Bardo Ave Office Bldg Pwr Pl Addn 1 Uploaded: 12/9/2024 (375 kb)
      • S83 Dtls Addn 1 Uploaded: 12/9/2024 (375 kb)
    • Addn 3
      • E11 Mechanical Rm-Lab-Utility RmCorridor Pwr Plan Addn 3.pdf Uploaded: 12/24/2024 (440 kb)
      • E26 Details Addn 3.pdf Uploaded: 12/24/2024 (530 kb)
      • H02 Water Treatment Bldg HVAC Plan Addn 3.pdf Uploaded: 12/24/2024 (1187 kb)
      • H81 HVAC Schedules Addn 3.pdf Uploaded: 12/24/2024 (343 kb)
  • Specifications
    • Agreement Uploaded: 12/9/2024 (198 kb)
    • Application for Payment Form Uploaded: 12/9/2024 (4103 kb)
    • BID FORM - WR1 General-Mechanical Work Uploaded: 12/9/2024 (162 kb)
    • BID FORM - WR2 Electrical Work Uploaded: 12/9/2024 (162 kb)
    • Bid Alternates Uploaded: 12/9/2024 (70 kb)
    • Bid Bond Uploaded: 12/9/2024 (282 kb)
    • Certificate of Substantial Completion Form Uploaded: 12/9/2024 (238 kb)
    • Certification of Non-Segregated Facilities Uploaded: 12/9/2024 (58 kb)
    • Certifications of Equal Employment Opportunities Uploaded: 12/9/2024 (92 kb)
    • Consent of Surety Company to Final Payment Uploaded: 12/9/2024 (67 kb)
    • Contractors Affidavit of Payment of Debts Claims Uploaded: 12/9/2024 (67 kb)
    • DBE Requirements Uploaded: 12/9/2024 (14336 kb)
    • Div 01 General Requirements Uploaded: 12/9/2024 (785 kb)
    • Div 02 Existing Conditions Uploaded: 12/9/2024 (213 kb)
    • Div 03 Concrete Uploaded: 12/9/2024 (467 kb)
    • Div 04 Masonry Uploaded: 12/9/2024 (216 kb)
    • Div 05 Metals Uploaded: 12/9/2024 (237 kb)
    • Div 06 Wood Plastics Composites Uploaded: 12/9/2024 (245 kb)
    • Div 07 Thermal Moisture Protection Uploaded: 12/9/2024 (345 kb)
    • Div 08 Openings Uploaded: 12/9/2024 (211 kb)
    • Div 09 Finishes Uploaded: 12/9/2024 (398 kb)
    • Div 10 Specialties Uploaded: 12/9/2024 (225 kb)
    • Div 11 Equipment Uploaded: 12/9/2024 (306 kb)
    • Div 22 Plumbing Uploaded: 12/9/2024 (655 kb)
    • Div 23 HVAC Uploaded: 12/9/2024 (469 kb)
    • Div 26 Electrical Uploaded: 12/9/2024 (1156 kb)
    • Div 27 Communications Uploaded: 12/9/2024 (104 kb)
    • Div 28 Electronic Safety Security Uploaded: 12/9/2024 (200 kb)
    • Div 31 Earthwork Uploaded: 12/9/2024 (338 kb)
    • Div 32 Exterior Improvements Uploaded: 12/9/2024 (277 kb)
    • Div 33 Utilities Uploaded: 12/9/2024 (231 kb)
    • Div 40 Process Interconnections Uploaded: 12/9/2024 (679 kb)
    • Div 42 Process Drying Equipment Uploaded: 12/9/2024 (111 kb)
    • Div 43 Process Gas Liquid Handling Purification Storage Equipment Uploaded: 12/9/2024 (510 kb)
    • Div 43 Water Wastewater Equipment Uploaded: 12/9/2024 (628 kb)
    • Federal State Requirements of the General Conditions Uploaded: 12/9/2024 (252 kb)
    • Form of Change Order Uploaded: 12/9/2024 (309 kb)
    • General Conditions of the Contract Uploaded: 12/9/2024 (757 kb)
    • Geotechnical Data Uploaded: 12/9/2024 (2711 kb)
    • Hold Harmless Agreement Uploaded: 12/9/2024 (72 kb)
    • Instructions to Bidders Uploaded: 12/9/2024 (134 kb)
    • Invitation to Bid Uploaded: 12/9/2024 (63 kb)
    • MBE-WBE Solicitation Uploaded: 12/9/2024 (19169 kb)
    • MBE-WBE Utilization Reports Affirmative Action Plan Uploaded: 12/9/2024 (1356 kb)
    • Non-Collusion Affidavit Uploaded: 12/9/2024 (51 kb)
    • Non-Collusion Affidavit of Prime Bidder Uploaded: 12/9/2024 (74 kb)
    • Payment Bond Uploaded: 12/9/2024 (254 kb)
    • Performance Bond Uploaded: 12/9/2024 (273 kb)
    • Permits Uploaded: 12/9/2024 (9829 kb)
    • Public Works Employment Verification Form Uploaded: 12/9/2024 (155 kb)
    • Qualifications Experience Equipment Financial Statement Uploaded: 12/9/2024 (84 kb)
    • Release of Lien Uploaded: 12/9/2024 (65 kb)
    • Steel Origin Certifications Uploaded: 12/9/2024 (251 kb)
    • Super Cross Cutter Requirements Uploaded: 12/9/2024 (870 kb)
    • Supplementary Conditions Uploaded: 12/9/2024 (300 kb)
    • Table of Contents Uploaded: 12/9/2024 (189 kb)
    • Thumbs Uploaded: 12/9/2024 (246 kb)
    • W-9 Form Uploaded: 12/9/2024 (138 kb)
    • Wage Rates Uploaded: 12/9/2024 (3776 kb)
    • _Combined Specifications Uploaded: 12/9/2024 (63567 kb)
  • Drawings
    • Architectural
      • A01 Code SumWTP Bldg OA Fl Pl Uploaded: 12/9/2024 (1181 kb)
      • A02 WTP Bldg Garage Fl Pl Uploaded: 12/9/2024 (410 kb)
      • A03 WTP Bldg Fl Pl Uploaded: 12/9/2024 (1243 kb)
      • A04 WTP Bldg Rf Pl Uploaded: 12/9/2024 (296 kb)
      • A05 WTP Bldg Ext Elvs Uploaded: 12/9/2024 (465 kb)
      • A06 Wall SectsDtls Uploaded: 12/9/2024 (473 kb)
      • A07 Wall Sects Uploaded: 12/9/2024 (435 kb)
      • A08 WTP Bldg Secs Uploaded: 12/9/2024 (754 kb)
      • A09 Restrm Pl-Sch-Dtls Uploaded: 12/9/2024 (400 kb)
      • A10 Lab Pl Uploaded: 12/9/2024 (332 kb)
      • A11 Lab Int Elvs Uploaded: 12/9/2024 (347 kb)
      • A12 Lab Int Elvs Uploaded: 12/9/2024 (310 kb)
      • A13 Lab SchDtls Uploaded: 12/9/2024 (445 kb)
      • A30 Raw Wtr Chem Fd Bldg Fl Pl Uploaded: 12/9/2024 (437 kb)
      • A31 Raw Wtr Chem Fd Bldg Rf Pl Uploaded: 12/9/2024 (281 kb)
      • A32 Raw Wtr Chem Fd Bldg Ext Elvs Uploaded: 12/9/2024 (574 kb)
      • A33 Raw Wtr Chem Fd Bldg SectsDtls Uploaded: 12/9/2024 (708 kb)
      • A80 Dr SchDtls Uploaded: 12/9/2024 (338 kb)
      • A81 Dr JambHead Dtls Uploaded: 12/9/2024 (399 kb)
      • A82 SchsDtls Uploaded: 12/9/2024 (765 kb)
      • A83 SchsDtls Uploaded: 12/9/2024 (388 kb)
    • Civil
      • C01 OA Exist Site PlLgnds Uploaded: 12/9/2024 (495 kb)
      • C02 Wtr Strg Tank Area-Exist Site Pl Uploaded: 12/9/2024 (542 kb)
      • C03 Lagoon Area-Exist Site Pl Uploaded: 12/9/2024 (569 kb)
      • C04 Filtr Plant Area-Exist Site Pl Uploaded: 12/9/2024 (785 kb)
      • C05 Sedi Basin Area-Exist Site Pl Uploaded: 12/9/2024 (708 kb)
      • C06 Wtr Strg Tank Area-Demo Site Pl Uploaded: 12/9/2024 (570 kb)
      • C07 Lagoon Area-Demo Site Pl Uploaded: 12/9/2024 (594 kb)
      • C08 Filtr Plant Area-Demo Site Pl Uploaded: 12/9/2024 (910 kb)
      • C09 Sedi Basin Area-Demo Site Pl Uploaded: 12/9/2024 (770 kb)
      • C10 Filtr Plant Area-Prop Clearwell Excav Pl Uploaded: 12/9/2024 (811 kb)
      • C11 Filtr Plant Area-Prop Site LO Pl Uploaded: 12/9/2024 (3103 kb)
      • C12 Sedi Basin Area-Prop Site LO Pl Uploaded: 12/9/2024 (2347 kb)
      • C13 Filtr Plant Area-Prop Reloc Wtr Co Rd Prof Uploaded: 12/9/2024 (331 kb)
      • C14 Wtr Strg Tank Area-Prop Site Piping Pl Uploaded: 12/9/2024 (600 kb)
      • C15 Lagoon Area-Prop Site Piping Pl Uploaded: 12/9/2024 (637 kb)
      • C16 Filtr Plant Area-Prop Site Piping Pl Uploaded: 12/9/2024 (3104 kb)
      • C17 Sedi Basin Area-Prop Site Piping Pl Uploaded: 12/9/2024 (1956 kb)
      • C18 Prop BaselineManhole Loc Geo-Yd Piping Sch-Notes Uploaded: 12/9/2024 (542 kb)
      • C19 Prop FittingManhole Loc Geo Uploaded: 12/9/2024 (441 kb)
      • C20 Comb DrainWW Hldg Tank Decant-Overflow-Sand Dry Beds-Fin Wtrline Profs Uploaded: 12/9/2024 (356 kb)
      • C21 Chem Fd Bldg DrainRaw Wtr Profs Uploaded: 12/9/2024 (362 kb)
      • C22 Chem Fd Bldg DrainSanit Profs Uploaded: 12/9/2024 (356 kb)
      • C23 Settled WtrlineSedi Basin Bypass Profs Uploaded: 12/9/2024 (308 kb)
      • C24 Strm SwrDownspout Drain Profs Uploaded: 12/9/2024 (391 kb)
      • C25 Fin Wtrline Profs-Bid Alt Uploaded: 12/9/2024 (316 kb)
      • C26 Filtr Plant Area-Prop Grdng Pl Uploaded: 12/9/2024 (3192 kb)
      • C27 Sedi Basin Area-Prop Grdng Pl Uploaded: 12/9/2024 (2408 kb)
      • C28 Prop Wtr Treatment Bldg Site Secs Uploaded: 12/9/2024 (329 kb)
      • C29 Prop Chem Fd Bldg Site Sects Uploaded: 12/9/2024 (262 kb)
      • CD01 Trench Dtls Uploaded: 12/9/2024 (457 kb)
      • CD02 Site Dtls Uploaded: 12/9/2024 (515 kb)
      • CD03 Site Dtls Uploaded: 12/9/2024 (602 kb)
      • CD04 Site Dtls Uploaded: 12/9/2024 (426 kb)
      • CD05 Site Dtls Uploaded: 12/9/2024 (474 kb)
      • CD06 ESC Dtls Uploaded: 12/9/2024 (620 kb)
      • CD07 ESC Dtls Uploaded: 12/9/2024 (529 kb)
      • CD08 ESC Notes Uploaded: 12/9/2024 (854 kb)
      • CD09 ESC Notes Uploaded: 12/9/2024 (656 kb)
      • CD10 ESC Notes Uploaded: 12/9/2024 (488 kb)
      • CD11 PCSM Dtls Uploaded: 12/9/2024 (615 kb)
      • CD12 PCSM Dtls Uploaded: 12/9/2024 (522 kb)
      • CD13 PCSM NotesDtls Uploaded: 12/9/2024 (1721 kb)
      • ESC-1 Wtr Strg Tank Area Pl Uploaded: 12/9/2024 (638 kb)
      • ESC-2 Lagoon Area Pl Uploaded: 12/9/2024 (688 kb)
      • ESC-3 Filtr Plant Area-Stg 1 Pl Uploaded: 12/9/2024 (1032 kb)
      • ESC-4 Filtr Plant Area-Stg 2 Pl Uploaded: 12/9/2024 (1082 kb)
      • ESC-5 Filtr Plant Area Stg 3 Pl Uploaded: 12/9/2024 (3258 kb)
      • ESC-6 Sedi Basin Area Pl Uploaded: 12/9/2024 (2001 kb)
      • PCSM-1 Wtr Strg Tank Area Pl Uploaded: 12/9/2024 (620 kb)
      • PCSM-2 Lagoon Area Pl Uploaded: 12/9/2024 (669 kb)
      • PCSM-3 Filtr Plant Area Pl Uploaded: 12/9/2024 (3174 kb)
      • PCSM-4 Sedi Basin Area Pl Uploaded: 12/9/2024 (1989 kb)
      • PCSM-5 Riparian Buffer Conserv Easement Pl Uploaded: 12/9/2024 (2381 kb)
      • PCSM-6 Riparian Buffer OffsettingMitig Pl Uploaded: 12/9/2024 (645 kb)
      • PCSM-7 Riparian Buffer Mitig NotesDtls Uploaded: 12/9/2024 (1925 kb)
      • PCSM-8 Bioretention Landscaping Pl Uploaded: 12/9/2024 (475 kb)
      • TB01 Filtr Plant Area-Prop TBInfiltr Pit Pl Uploaded: 12/9/2024 (943 kb)
      • TB02 Sedi Basin Area Pl Uploaded: 12/9/2024 (609 kb)
      • TB03 Logs Uploaded: 12/9/2024 (6920 kb)
    • Demolition
      • D50 Roaring Run Mtr Vlt Demo Pl Uploaded: 12/9/2024 (305 kb)
      • D70 Exist Sedi Basin Demo Pl Uploaded: 12/9/2024 (351 kb)
    • Electrical
      • E01 LgndAbbrevs Uploaded: 12/9/2024 (670 kb)
      • E02 Filtr Plant Area-Prop Elec Site LO Pl Uploaded: 12/9/2024 (969 kb)
      • E03 Sedi Basin Area-Prop Site LO Elec Pl Uploaded: 12/9/2024 (2408 kb)
      • E04 Wtr Strg Tank Area-Prop Site Elec Pl Uploaded: 12/9/2024 (596 kb)
      • E05 Wtr Strg Tank Area-Exist Shed Pwr PlsDtls Uploaded: 12/9/2024 (404 kb)
      • E06 Site Pl Conduit Sch Uploaded: 12/9/2024 (365 kb)
      • E06 Site Pl Conduit Sch Addn 1-1 Uploaded: 12/9/2024 (335 kb)
      • E07 Site Pl Conduit Sch Uploaded: 12/9/2024 (374 kb)
      • E08 OA Elec Fl Pl Uploaded: 12/9/2024 (1189 kb)
      • E09 Process AreaElec Rm Pwr Pl Uploaded: 12/9/2024 (1241 kb)
      • E09 Process AreaElec Rm Pwr Pl Addn 1-1 Uploaded: 12/9/2024 (1219 kb)
      • E10 Chem FdStrg Rm-RestrmJanitor Closet Pwr Pl Uploaded: 12/9/2024 (565 kb)
      • E10 Chem FdStrg Rm-RestrmJanitor Closet Pwr Pl Addn 1-1 Uploaded: 12/9/2024 (543 kb)
      • E11 Mech Rm-Lab-Utility Rm-Corridor Pwr Pl Uploaded: 12/9/2024 (468 kb)
      • E12 WTP Bldg Garage Fl Pwr Pl Uploaded: 12/9/2024 (522 kb)
      • E13 Clearwell-WW Hldng Tank Sepn Area PwrLtg Pls Uploaded: 12/9/2024 (428 kb)
      • E14 OA Ltg Pl Uploaded: 12/9/2024 (1217 kb)
      • E15 Photometric Pl Uploaded: 12/9/2024 (2621 kb)
      • E16 OA WTP Sec Pl Uploaded: 12/9/2024 (1183 kb)
      • E16 OA WTP Sec Pl Addn 1-1 Uploaded: 12/9/2024 (1157 kb)
      • E17 Raw Wtr Chem Fd Bldg Pwr Pl Uploaded: 12/9/2024 (556 kb)
      • E17 Raw Wtr Chem Fd Bldg Pwr Pl Addn 1-1 Uploaded: 12/9/2024 (533 kb)
      • E18 Raw Wtr Chem Fd Bldg Ltg Pl Uploaded: 12/9/2024 (525 kb)
      • E19 Vlt PwrLtg Pls Uploaded: 12/9/2024 (369 kb)
      • E20 Exist Sedi Basin Modif Pwr Pl Uploaded: 12/9/2024 (404 kb)
      • E21 Single Line Riser Diag Uploaded: 12/9/2024 (400 kb)
      • E22 Pnl Sch-VFD SchPhone Serv One Line Uploaded: 12/9/2024 (411 kb)
      • E23 Pnl Sch Uploaded: 12/9/2024 (412 kb)
      • E24 Pnl Schs Uploaded: 12/9/2024 (410 kb)
      • E24 Pnl Schs Addn 1-1 Uploaded: 12/9/2024 (387 kb)
      • E25 Lgt Fixture SchDtls Uploaded: 12/9/2024 (558 kb)
      • E25 Lgt Fixture SchDtls Addn 1-1 Uploaded: 12/9/2024 (650 kb)
      • E26 Dtls Uploaded: 12/9/2024 (557 kb)
      • E26 Dtls Addn 1-1 Uploaded: 12/9/2024 (529 kb)
      • E27 Typ OutletConduit Penetration Dtls Uploaded: 12/9/2024 (497 kb)
      • E30 Bardo Ave Office Bldg-Prop Gen Site LO Pl Uploaded: 12/9/2024 (297 kb)
      • E31 Bardo Ave Office Bldg Pwr Pl Uploaded: 12/9/2024 (305 kb)
      • E31 Bardo Ave Office Bldg Pwr Pl Addn 1-1 Uploaded: 12/9/2024 (375 kb)
    • Plumbing
      • P01 WTP Bldg DWV Pl Uploaded: 12/9/2024 (1208 kb)
      • P02 WTP Bldg Potable Wtr Supp Pl Uploaded: 12/9/2024 (1226 kb)
      • P03 WTP Bldg Propane Supp Pl Uploaded: 12/9/2024 (1192 kb)
      • P30 Raw Wtr Chem Fd Bldg Pl Uploaded: 12/9/2024 (376 kb)
      • P80 SchsDtls Uploaded: 12/9/2024 (517 kb)
      • P81 Dtls Uploaded: 12/9/2024 (368 kb)
    • Structural
      • S01 Clearwell-WW Hldng TankSepn Area Fnd Pl Uploaded: 12/9/2024 (384 kb)
      • S02 Clearwell-WW Hldng Tank-Sepn Area WallGrout Pl Uploaded: 12/9/2024 (374 kb)
      • S03 WTP Bldg FootingTrench Pl Uploaded: 12/9/2024 (437 kb)
      • S04 WTP Bldg Slab Pl Uploaded: 12/9/2024 (479 kb)
      • S05 WTP Bldg Trench Drain-Access HatchEquip Pad Pl Uploaded: 12/9/2024 (476 kb)
      • S06 WTP Bldg GratingRailing Pl Uploaded: 12/9/2024 (549 kb)
      • S07 WTP Bldg PlasterWall Cntrl Joint Pl Uploaded: 12/9/2024 (481 kb)
      • S08 WTP Bldg Rf Frmg Pl Uploaded: 12/9/2024 (358 kb)
      • S10 Clearwell-WW Hldng TankSepn Area Sects Uploaded: 12/9/2024 (544 kb)
      • S11 Clearwell-WW Hldng TankSepn Area Sects Uploaded: 12/9/2024 (562 kb)
      • S12 Clearwell-WW Hldng TankSepn Area Sects Uploaded: 12/9/2024 (563 kb)
      • S13 WTP Bldg Sects Uploaded: 12/9/2024 (490 kb)
      • S14 WTP Bldg Sects Uploaded: 12/9/2024 (379 kb)
      • S15 WTP Bldg Sects Uploaded: 12/9/2024 (376 kb)
      • S16 WTP Bldg Sects Uploaded: 12/9/2024 (354 kb)
      • S17 WTP Bldg Sects Uploaded: 12/9/2024 (416 kb)
      • S18 WTP Bldg Sects Uploaded: 12/9/2024 (430 kb)
      • S20 Precase Conc Chem Containment Pit PlsSects Uploaded: 12/9/2024 (489 kb)
      • S30 Raw Wtr Chem Fd Bldg Fnd Pl Uploaded: 12/9/2024 (331 kb)
      • S31 Raw Wtr Chem Fd Bldg Slab Pl Uploaded: 12/9/2024 (350 kb)
      • S32 Raw Wtr Chem Fd Bldg Rf Frmg Pl Uploaded: 12/9/2024 (325 kb)
      • S33 Raw Wtr Chem Fd Bldg Sects Uploaded: 12/9/2024 (518 kb)
      • S80 Dtls Uploaded: 12/9/2024 (450 kb)
      • S81 StrRailing Dtls Uploaded: 12/9/2024 (387 kb)
      • S82 Dtls Uploaded: 12/9/2024 (421 kb)
      • S83 Dtls Uploaded: 12/9/2024 (366 kb)
      • S83 Dtls Addn 1-1 Uploaded: 12/9/2024 (375 kb)
      • S84 Excav DtlsNotes Uploaded: 12/9/2024 (733 kb)
    • General
      • CS-1 Cvr Sht Uploaded: 12/9/2024 (1451 kb)
      • CS-2 Dwg Index Uploaded: 12/9/2024 (473 kb)
      • CS-3 NotesRefs Uploaded: 12/9/2024 (792 kb)
      • CS-4 PA One Call Info-Surv CntrlSite Notes Uploaded: 12/9/2024 (648 kb)
      • G01 Prop Process Flow Schm Uploaded: 12/9/2024 (422 kb)
      • G02 Prop Hydraulic Prof Uploaded: 12/9/2024 (284 kb)
    • HVAC
      • H01 HVAC Symbs-Notes-Abbrevs Uploaded: 12/9/2024 (624 kb)
      • H02 WTP Bldg Pl Uploaded: 12/9/2024 (1212 kb)
      • H30 Raw Wtr Chem Fd Bldg Pl Uploaded: 12/9/2024 (375 kb)
      • H80 Schs Uploaded: 12/9/2024 (349 kb)
      • H81 Schs Uploaded: 12/9/2024 (365 kb)
      • H82 Dtls Uploaded: 12/9/2024 (295 kb)
    • Mechanical
      • M01 OA Pl Uploaded: 12/9/2024 (1229 kb)
      • M02 Process Area Pl Uploaded: 12/9/2024 (1301 kb)
      • M03 Chem FdStrg Rm Pl Uploaded: 12/9/2024 (751 kb)
      • M04 Rm Pl Uploaded: 12/9/2024 (423 kb)
      • M05 Utility Rm Pl Uploaded: 12/9/2024 (423 kb)
      • M06 Clearwell WW Hldng TankSepn Area Pl Uploaded: 12/9/2024 (563 kb)
      • M07 Sects Uploaded: 12/9/2024 (655 kb)
      • M08 Sects Uploaded: 12/9/2024 (741 kb)
      • M09 Sects Uploaded: 12/9/2024 (384 kb)
      • M10 Sects Uploaded: 12/9/2024 (417 kb)
      • M11 Sects Uploaded: 12/9/2024 (412 kb)
      • M12 Sects Uploaded: 12/9/2024 (392 kb)
      • M13 Sects Uploaded: 12/9/2024 (380 kb)
      • M14 Sects Uploaded: 12/9/2024 (460 kb)
      • M15 Sects Uploaded: 12/9/2024 (512 kb)
      • M16 Sects Uploaded: 12/9/2024 (589 kb)
      • M17 Sects Uploaded: 12/9/2024 (438 kb)
      • M18 Sects Uploaded: 12/9/2024 (319 kb)
      • M19 Sects Uploaded: 12/9/2024 (380 kb)
      • M20 Sects Uploaded: 12/9/2024 (362 kb)
      • M21 Sects Uploaded: 12/9/2024 (415 kb)
      • M22 Sects Uploaded: 12/9/2024 (424 kb)
      • M23 Sects Uploaded: 12/9/2024 (413 kb)
      • M24 Process Area Pipe Supp Pl Uploaded: 12/9/2024 (1173 kb)
      • M25 Chem FdStrg Rm Pipe Supp Pl Uploaded: 12/9/2024 (535 kb)
      • M26 MechUtility Rms Pipe Supp Pl Uploaded: 12/9/2024 (371 kb)
      • M27 WW Hldng TankSepn Area Pipe Supp Pl Uploaded: 12/9/2024 (370 kb)
      • M30 Raw Wtr Chem Fd Bldg Pl Uploaded: 12/9/2024 (550 kb)
      • M31 Raw Wtr Chem Fd Bldg Sects Uploaded: 12/9/2024 (533 kb)
      • M32 Raw Wtr Chem Fd Bldg Sect Uploaded: 12/9/2024 (454 kb)
      • M33 Raw Wtr Chem Fd Bldg Pipe Supp Pl Uploaded: 12/9/2024 (416 kb)
      • M50 Roaring Run Mtr Vlt Modif Pl Uploaded: 12/9/2024 (336 kb)
      • M55 Raw Wtr MtrChem Inject Vlt PlsSects Uploaded: 12/9/2024 (635 kb)
      • M60 Sand Dry Beds Pl-Sects-Dtls Uploaded: 12/9/2024 (398 kb)
      • M61 Sand Dry Beds SectsDtls Uploaded: 12/9/2024 (1073 kb)
      • M70 Exist Sedi Basin Modif Pl-Sect-Dtl Uploaded: 12/9/2024 (459 kb)
      • M80 Int Process Piping Sch Uploaded: 12/9/2024 (428 kb)
      • M81 Dtls Uploaded: 12/9/2024 (424 kb)
      • M82 Dtls Uploaded: 12/9/2024 (443 kb)
      • M83 Slide Gate SchDtls Uploaded: 12/9/2024 (414 kb)
      • M84 Dtls Uploaded: 12/9/2024 (375 kb)
      • M85 Air Piping SchmDtls Uploaded: 12/9/2024 (420 kb)
      • M86 Instm Schs Uploaded: 12/9/2024 (529 kb)
      • M87 Instm Schs Uploaded: 12/9/2024 (392 kb)
      • M88 Dtls Uploaded: 12/9/2024 (396 kb)
      • M89 Typ Process Chem Day Tank DtlSch Uploaded: 12/9/2024 (362 kb)
      • M90 Typ Bulk Strg TankSchmSch Uploaded: 12/9/2024 (336 kb)
      • M91 Membrane Filtrs Piping Supp Dtls Uploaded: 12/9/2024 (401 kb)
      • M92 Piping Supp Dtls Uploaded: 12/9/2024 (386 kb)
    • _Combined Drawings Uploaded: 12/9/2024 (141733 kb)

Project Info

Project # 24-045
Project Name GC - Larry's Creek Water Treatment Plant
Location Jersey Shore Area Joint Water Authority
Address Map It 977 Water Company Road
City Jersey Shore
State PA
Zip 17740
Bid Date January 8, 2025
Bid Time 12:00 PM
 
Scope

This project consists of the construction of a new 2.0 million gallon per day capacity water treatment facility including earthwork, access roads, mechanical piping and equipment, membrane filtration system (cartridge type), chemical feed and storage systems, finish water clearwell, wastewater holding tanks, solids drying beds, a chemical pretreatment building, water transmission main, yard piping, instrumentation control and monitoring system, HVAC work, plumbing work, building architectural work, structural steel and reinforced concrete construction, site improvements and all required appurtenances.

 
 
Plans
Other Info We are requesting quotes for the following Specification Sections:

DIVISION 02 - EXISTING CONDITIONS

Section 02 11 00: Demolition
Section 02 41 00: Selective Demolition

DIVISION 03 - CONCRETE

Section 03 11 00: Concrete Forming and Accessories
Section 03 20 00: Concrete Reinforcing
Section 03 30 00: Cast-In-Place Concrete
Section 03 41 00: Precast, Prestressed Structural Concrete
Section 03 62 00: Non-Shrink Grouting

DIVISION 04 - MASONRY

Section 04 05 13: Masonry Mortars
Section 04 22 00: Concrete Unit Masonry

DIVISION 05 - METALS

Section 05 12 00: Structural Steel
Section 05 12 13: Miscellaneous Metals
Section 05 14 00: Structural Aluminum
Section 05 52 00: Aluminum Handrail, Grating, Stair Tread, and Access Hatches

DIVISION 06 - WOOD, PLASTICS AND COMPOSITES

Section 06 10 00: Rough Carpentry
Section 06 11 00: Wood Framing
Section 06 17 53: Plate Connected Wood Trusses
Section 06 80 00: Structural Fiberglass Reinforced Plastic
Section 06 81 00: Fiberglass (FRP) Grating, Ladders, Handrail and Stairs

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

Section 07 16 16: Crystalline Waterproofing
Section 07 21 00: Building Insulation and Vapor Barrier
Section 07 42 93: Vinyl Ceiling
Section 07 46 00: Siding, Soffit, and Fascia
Section 07 61 13: Aluminum Standing Seam Roofing
Section 07 71 23: Gutters and Downspouts
Section 07 84 00: Firestopping
Section 07 92 00: Joint Sealants

DIVISION 08 - OPENINGS

Section 08 16 13: Fiberglass Reinforced Plastic Doors, Panels and Frames
Section 08 33 23: Overhead Coiling Doors
Section 08 71 00: Finish Hardware
Section 08 80 00: Glass and Glazing

DIVISION 09 - FINISHES

Section 09 29 00: Gypsum Wallboard Systems
Section 09 50 00: Vinyl Ceiling
Section 09 51 23: Suspended Acoustical Ceiling
Section 09 62 19: Laminate Flooring System
Section 09 91 23: Painting

DIVISION 10 - SPECIALTIES

Section 10 14 00: Identifying Devices
Section 10 28 13: Toilet Accessories
Section 10 40 00: Building Specialties
Section 10 51 13: Metal Lockers

DIVISION 11 - EQUIPMENT

Section 11 00 00: Equipment General Provisions
Section 11 05 13: Motors
Section 11 53 00: Laboratory Furniture, Apparatus, Instruments and Supplies

DIVISION 22 - PLUMBING

Section 22 05 05: Plumbing Basic Materials
Section 22 05 10: Plumbing Pipe and Pipe Fittings
Section 22 05 16: Drainage and Vent Systems
Section 22 05 19: Tri-Gauges
Section 22 05 20: Plumbing Specialties
Section 22 05 25: Plumbing Valves
Section 22 05 29: Supports and Anchors
Section 22 05 53: Plumbing Identification
Section 22 05 53.13: Mechanical Identification and Painting
Section 22 07 19: Plumbing Insulation
Section 22 10 05: Domestic Water Piping
Section 22 10 06: Plumbing Piping Specialties
Section 22 11 26: Facility Liquefied-Petroleum Gas Piping
Section 22 40 00: Plumbing Fixtures
Section 22 40 01: Trench Drains

DIVISION 23 - HEATING, VENTILATION AND AIR-CONDITIONING (HVAC)

Section 23 05 00: Basic Requirements for HVAC Work
Section 23 05 93: Testing, Adjusting, and Balancing For HVAC
Section 23 07 13: Duct Installation
Section 23 08 00: Commissioning of HVAC
Section 23 23 00: Refrigeration Piping Systems
Section 23 31 00: HVAC Ducts and Casings
Section 23 34 00: Exhaust Fans
Section 23 37 13: Air Outlets and Inlets
Section 23 55 33: Fuel-Fired Unit Heater
Section 23 62 46: Variable Refrigerant Flow Units
Section 23 82 39: Electrical Heating Equipment
Section 23 84 16: Mechanical Dehumidification Units

DIVISION 31 - EARTHWORK

Section 31 00 00: Site Work General Provisions
Section 31 11 00: Clearing and Grubbing
Section 31 20 00: Earthmoving
Section 31 22 19.13: Topsoil, Seeding, and Mulching
Section 31 23 19: Dewatering
Section 31 25 00: Erosion and Sediment Control

DIVISION 32 - EXTERIOR IMPROVEMENTS

Section 32 16 00: Paving, Surfacing, Walkways and Curbs
Section 32 31 12: Chain Link Cantilever Slide Gates
Section 32 31 13: Chain Link Fence and Gates
Section 32 94 00: Trees, Plants, and Other Restoration

DIVISION 33 - UTILITIES

Section 33 01 10.58: Disinfection of Water Treatment Facility
Section 33 01 12: Piping System Testing and Disinfection
Section 33 05 31.11: Non pressure PVC Pipe
Section 33 05 31.13: PVC Pressure Pipe
Section 33 05 31.35: PVC/CPVC Valves
Section 33 05 33.13: Corrugated Polyethylene Pipe

DIVISION 40 - PROCESS INTERCONNECTIONS

Section 40 00 00: Piping System General Provisions
Section 40 05 07: Hangers and Supports for Process Piping
Section 40 05 17: Copper Pipe
Section 40 05 19: Ductile Iron Pipe
Section 40 05 23: Stainless Steel Pipe
Section 40 05 24: Steel Pipe
Section 40 05 51: Valves General Provisions
Section 40 05 59.23: Slide Gates
Section 40 05 61: Gate Valves
Section 40 05 62: Plug Valves
Section 40 05 64: Butterfly Valves
Section 40 05 65: Check Valves
Section 40 79 00: Miscellaneous Valves and Piping Specialties
Section 40 98 00: Piping System Appurtenances

DIVISION 42 - PROCESS DRYING EQUIPMENT

Section 42 30 00: Sand Drying Beds

DIVISION 43 - PROCESS GAS AND LIQUID HANDLING, PURIFICATION AND STORAGE EQUIPMENT

Section 43 23 01: Pumping Equipment
Section 43 41 13: Caustic Soda Welded Steel Chemical Storage Tanks
Section 43 41 43: Flat Bottom, High-Density Crosslinked Polyethylene Bulk Chemical Storage Tanks
Section 43 41 45: Sodium Hypochlorite FRP Chemical Storage Tanks

DIVISION 46 - WATER AND WASTEWATER EQUIPMENT

Section 46 33 00: Liquid Chemical Feed Systems
Section 46 41 11: Vertical Shaft Turbine Mixers
Section 46 61 33: Packaged Microfiltration System



Notices

If you are looking for attached files related to a Notice, go back to the Home tab ("Project Files" are on the right side).
Title Created By Created On
Larry's Creek Water Treatment Plant Pat Smith 11/11/2024
Notice of Addendum 1 and Bid Extension Valerie Slagle 12/9/2024
Notice of Addendum 2 and Bid Extension Diane Womelsdorf 12/13/2024
Notice of Addendum 3 Diane Womelsdorf 12/24/2024

Estimators

Company Estimator Phone Extension Fax Email
Lobar, Inc Aaron Eichelberger 717-432-9728 AaronE@lobar.com
Lobar, Inc. Eric Bowen 717-432-9728 4289 eric.bowen@lobar.com
Lobar, Inc. Matt Ayers 717-432-9728 4209 MattA@lobar.com

If you have project-related questions, please contact your contractor or use the "Submit Question" tab.