Project Info
|
| Project # |
|
|
Project Name
|
BURLINGTON ENTRANCE REMODEL-PHILADELPHIA-PA
|
|
Location
|
7301 CASTOR AVE, PHILADELPHIA, PA 19152
|
|
Address
|
Map It
7301 CASTOR AVE.
|
|
City
|
PHILADELPHIA
|
|
State
|
PA
|
|
Zip
|
19152
|
|
Bid Date
|
August 19, 2020
|
|
Bid Time
|
5:00 PM
|
|
|
| Scope |
FLYNN CONSTRUCTION WOULD LIKE TO INVITE YOU FIRM TO BID ON THE BURLINGTON -ENTRANCE REMODEL IN PHILADELPHIA, PA. THIS PROJECT IS A MINOR RENOVATION TO AN EXISTING BURLINGTON LOCATION. THE BURLINGTON IS IN THE COTTMAN & CASTOR SHOPPING CENTER LOCATED AT 7301 CASTOR AVE IN PHILADELPHIA, PA. THE PROJECT IS TO SEAL OFF ONE ENTRANCE AND COVERT THE INTERIOR INTO SALES AREA. ALL WORK WILL BE PRERFORMED OVERNIGHT. YOUR BASE BID SHOULD INCLUDE 1 PHASE. PROVIDE AN ALTERNATE IF THE WORK IS TO BE DONE IN 2 PHASES. PHASE 1 WILL BE FROM THE CENTER COLUMN LINE (SOUTH WALL OF THE VESTIBULE) NORTH TO THE CART CORRAL. PHASE 2 WILL BE FROM THE CENTER COLUMN LINE SOUTH TO THE LAYAWAY ENTRANCE.
TRADES NEEDED:
DEMOLITION (WALLS, FLOORING, CEILING, LIGHTS, VESTIBULE HEATERS, VESTIBULE, ETC0ALTERNATE TO DEMO STOREFRONT SYSTEM) CONCRETE (SCARIFY & POUR SLAB TO LEVEL WITH ADJACENT AREAS) EIFS (INFILL STOREFRONT AREA) DRYWALL/ROUGH CARPENTRY/ ACT (PARTITIONS, DRYWALL LEVEL 5 FINISH, BLOCKING, FIXTURE INSTALL, ACT GRID & TILE, ETC...) FLOORING (INSTALL LVT-OWNER TO PROVIDE LVT & ADHESIVES-YOU PROVIDE THE TRANSITIONS, RUBBER BASE & RUBBER BASE ADHESIVE) PAINTING (INTERIOR WALLS-PAINT FROM COLUMN TO COLUMN, NOT JUST NEW WORK ARE-ALTERNATE TO PAINT EIFS TO MATCH ADJACENT TAN BRICK) WINDOW TREATMENTS (BLACK OUT TINT ON STOREFRONT WINDOWS) SPRINKLERS (RAISE EXISTING HEADS FOR NEW CEILING HEIGHT) HVAC (MODIFY DUCTWORK FOR NEW CEILING) ELECTRICAL (ADD OWNER PROVIDED LIGHTS, RELOCATE LIGHTS, ETC...) FIRE ALARM (MODIFY SYSTEM FOR NEW LAYOUT)
|
| Plans |
IN ORDER TO OBTAIN THE PLANS, PLEASE FOLLOW THESE INSTRUCTIONS:
1. Click on the link in this email that says RESPOND AND VIEW PLANS 2. Enter the Project Key and Security Key Codes where prompted (this info can be found at the bottom of this email) 3. Click on the tab that says PROJECT FILES 4. Here you can downloand the plans Titled: PLANS
|
| Other Info |
PROJECT NOTES:
1. TYPICAL PROJECT SCHEDULES FOR 3-4 WEEKS.
2. THIS PROJECT WILL BE DONE UTILIZING OPEN SHOP TRADES.
3. PROJECT IS SCHEDULED TO START END OF SEPTEMBER.
4. ALL TRADES SHOULD INCLUDE PERMIT FEES IN THEIR PROPOSALS AS APPLICABLE.
5. ALL SUBCONTRACTORS WORKING WITH FLYNN CONSTRUCTION ARE REQUIRED TO CARRY WORKMANS COMP INSURANCE.
6. ALL SUBCONTRACTORS SHOULD CARRY APPLICABLE TAXES IN THIER QUOTE.
7. PLEASE DO NOT CONTACT THE ARCHITECT OR OWNER WITH ANY PROJECT QUESTIONS. AL QUESTIONS GO TO FLYNN CONSTRUCTION.
8. DROPBOX LINK TO DRAWINGS BELOW:
9. ALL WORK TO BE DONE OVERNIGHT.
10. YOUR BASE BID SHOULD INCLUDE 1 PHASE, PROVIDE AN ALTERNATE IF THE WORK IS TO BE DONE IN 2 PHASES. PHASE 1 WILL BE FROM THE CENTER COLUMN LINE SOUTH WALL OF THE VESTIBULE NORTH TO THE CART CORRAL. PHASE 2 WILL BE FROM THE CENTER COLUMN LINE SOUTH TO THE LAYAWAY ENTRANCE.
11. SCOPE SHEETS FOR TRADES BASED ON DRAWINGS WILL BE COMPLETED BY FLYNN & SENT AT A LATER DATE.
12. FLYNN WILL NOT BE CONDUCTING ON SITE VISITS OF THE SPACE-THE STORE IS OPEN AND CAN BE VISITED DURNING BUSINESS HOURS TO SEE THE AREA OF THE WORK.
13. VALUE ENGINEERING IDEAS AND ASSOCIATED COST SAVINGS ARE ALWAYS WELCOME. PLEASE THINK ABOUT ANY IDEAS YOU MAY HAVE AND PRESENT THEM WITH YOUR BID.
14. SEND ALL QUESTIONS REGARDING OBTAINING BID DOUCUMENTS TO BID DEPARTMENT AT BIDDEPT@FLYNN-CONSTRUCTION.COM
15. SEND ALL PROJECT QUESTIONS VIA EMAIL TO CONTACT BELOW:
JOE CERAR- JCERAR@FLYNN-CONSTRUCTION.COM (DIRECT DIAL) 412-342-0545 (CELL) 412-738-4942.
16. FLYNN IS LOOKING FOR SERIOUS AND QUALIFIED BIDDERS ONLY. WE ONLY ADD A FEW TO OUR BID LIST SO PLEASE LET US KNOW IF YOU ARE NOT ABLE TO QUOTE FOR ANY REASON SO THAT WE CAN SUPPLEMENT YOUR COMPANY WITH ANOTHER.
17. ALL BID PROPOSALS ARE TO BE EMAILED TO BIDDEPT@FLYNN-CONSTRUCTION.COM OR FAXED TO: 412-243-7925
|
|