Project Info
|
Project # |
|
Project Name
|
Norfolk Southern W-Line Arch Replacements
|
Location
|
Albion, IL to Mt. Vernon, IL
|
Address
|
|
City
|
|
State
|
IL
|
Zip
|
62864
|
Bid Date
|
February 21, 2023
|
Bid Time
|
11:00 AM
|
Site Meeting Date
|
February 7, 2023
|
Site Meeting Time
|
9:00 AM
|
|
|
Scope |
There are three bridges on this project at three different locations (MP 86.83-W, MP 92.60-W, and MP 135.11-W). The scope of work includes:
- The work shall consist of determining and developing construction access and span change-out methods
- Driving 2 H-pile piers and 2 H pile abutments
- Rock Socketing the Piles as described in the plans
- Furnishing and erecting Prestressed concrete single void box girders
- Furnishing and erecting precast concrete caps and backwall units as detailed in the plans;
- Removing and demoing the existing concrete arches
- Assisting railway forces with ballast and track placement during span change-out operations.
|
Plans |
|
Other Info |
Millstone Weber respectfully requests that all subcontractor and vendor proposals be submitted by February. 20th, 2023 at 11:00 AM CT so that we have time to contact you with any questions/clarifications. Bids may be submitted to bids@millstoneweber.com or through PipelineSuite. Please acknowledge all addendums with your proposal.
|
|