ALL WORK MUST BE COMPLETED WITHIN THE SCHEDULE NOTED. The Work shall be
conducted in a single phase as described in the schedule below:
July 10, 2024: Pre-Bid Conference at 2:00 p.m. (CDT) at Central Community College – Grand
Island, Center for Health and Technical Science at 3134 West Highway 34, Grand Island,
Nebraska 68802.
July 23, 2024: Bids received from General Contractors at 2:00 p.m. (CDT)
TBD, 2024: Contractors interviews in Central Community College - Grand Island, College
Administration, Board Room 80.
August 15, 2024: Low bid contractor recommendation presented to Board of Governors.
August 22, 2024: Contract awarded. Start Digital Document Submittal Service (ORACLE,
Submittal Exchange) and Administrative Requirements.
September 3, 2024: Construction Starts.
November 7, 2025: Substantial Completion.
December 1, 2025: Final Completion.
|