Wake Forest Water Main Replacement & Repair

Project Files

  • Plans
    • 2024-12 RFB WF WL Construction Plan Set_signed.pdf Uploaded: 1/2/2025 (165572 kb)
  • Specifications
    • 2024-12 RFB WF WL Front End Manual_signed.pdf Uploaded: 1/2/2025 (10445 kb)
    • 2024-12 RFB WF WL Tech Spec Manual_signed.pdf Uploaded: 1/2/2025 (13438 kb)
  • Addenduem
    • Addendum 1.pdf Uploaded: 1/2/2025 (657 kb)
    • Addendum 2.pdf Uploaded: 1/8/2025 (1133 kb)

Project Info

Project # WS-2014-117
Project Name Wake Forest Water Main Replacement & Repair
Location Raleigh, NC
Address
City
State
Zip
Bid Date January 15, 2025
Bid Time 2:00 PM
 
Scope The project includes the following:
• Water Infrastructure: 
     o Installing 9,900 LF of 4”, 6”, 8”, and 12” water main and appurtenances. 
     o Installing 300 water service change overs with 85 being via trenchless means. 
     o Installing 300 water meter and box replacements. 
     o Abandoning 19,050 LF of existing 1.5”, 2”, 6”, and 8” water main. 
     o Removal and disposal of 1,575 LF of 1.5” and 6” water main. 
• Wastewater Infrastructure: 
    o Installing 3,750 LF of 8” gravity sewer main and 18 manholes. 
    o Installing 105 sewer lateral service replacements with 3 being via trenchless means. 
    o Installing 195 LF of sewer lateral adjustment adjacent to CSXT ROW 
    o Installing 533 LF of sewer lateral re-routing 
    o Installing 2,250 LF of sanitary sewer lateral service CIPP lining 
    o Removal and disposal of 3,275 LF of 6” and 8” gravity sewer and 11 manholes  
• Storm Drainage Infrastructure 
    o Installing 725 LF of 12”, 15”, 18”, and 24” storm pipe and 17 storm structures. 
    o Removal and disposal of 725 LF of 12”, 15”, 18”, and 24” storm pipe and 17 storm structures. 
• Miscellaneous 
    o Installing appropriate E&S measures. 
    o Installing 43,340 SY of 2-inch asphalt roadway milling and overlay. 
    o Installing 9,995 SY of full depth asphalt pavement repair. 
    o Removal and replacement of 11,890 SY of Asphalt pavement.  
    o Removal and replacement of 190 LF of Granite Curb to Wake Forest Historic District Standard. 
    o Removal, replacement, and installation of 76 concrete curb ramps to ADA compliance. 
    o All associated efforts to return the site to pre-construction conditions. 
• Add Alternate Bid #1 
    o Abandon 470 LF of 1.5” Galvanized water main along N. White Street between E. Cedar Avenue and Lee Street
       and replace with approximately 500 LF of 6-inch ductile iron water main, appurtenances, and fittings.  
Plans
Other Info In order to encourage minority and women business enterprise subcontractors to participate in the bidding process, CCI will consider the following option/actions if required and requested in the proposal: assistance in obtaining bonding or insurance; coordinating joint pay agreements; assisting in obtaining the same unit pricing for supplies as is available to the contractor; coordinating bi-weekly pay agreements.  Subcontractors can bid work for this project in any areas that they are qualified. 

Notices

If you are looking for attached files related to a Notice, go back to the Home tab ("Project Files" are on the right side).
Title Created By Created On
Addendum Notice Chad Green 1/8/2025

Estimators

Company Estimator Phone Extension Fax Email
Carolina Civilworks Inc. Chad Green 919-598-9850 919-598-9912 cgreen@carolinacivilworks.com

If you have project-related questions, please contact your contractor or use the "Submit Question" tab.
If you are having technical difficulties downloading, please email support@pipelinesuite.com or call 949-222-0400.