NCMT Berth 24-11 Structural Repair

Project Files

  • Add01
    • 20260730093116021 2022-23_Addendum_No1_Full Set 2.pdf Uploaded: 7/30/2026 (77749 kb)
  • 01_Granite Agreements and Insurance Requirements
    • Granite Insurance Requirements Job Specific 2025.pdf Uploaded: 6/8/2026 (238 kb)
    • Professional_Services_Agreement.pdf Uploaded: 6/8/2026 (238 kb)
    • Project_Subcontract_Agreement.pdf Uploaded: 6/8/2026 (258 kb)
    • Purchase_Order_Long_Form.pdf Uploaded: 6/8/2026 (278 kb)
    • Purchase_Order_Short_Form.pdf Uploaded: 6/8/2026 (305 kb)
    • Safety Requirements.pdf Uploaded: 6/8/2026 (73 kb)
  • 20260604161006697 Notice of Inviting Bids for 2022-23 - NCMTBerth24-11 Structual Repair.pdf Uploaded: 6/8/2026 (229 kb)
  • 20260604161011853 BID PROPOSAL PACKAGE.pdf Uploaded: 6/8/2026 (754 kb)
  • 20260604161013325 Drawing No. NC-2022-02 NCMT Berth 24-11 StructReprSDCA 1.pdf Uploaded: 6/8/2026 (35327 kb)
  • 20260604161256899 Specification No. 2022-23 - NCMT Berth 24-11 Structural Repair 1.pdf Uploaded: 6/8/2026 (45015 kb)

Project Info

Project # 2022-23
Project Name NCMT Berth 24-11 Structural Repair
Location Port of San Diego
Address
City
State
Zip
Bid Date August 6, 2026
Bid Time 2:00 PM
 
Scope

Estimator:  Jerry Lynch at estimating.scr@gcinc.com or (760) 444-1028 or fax (805) 335-8912.

 

For proper consideration, please submit your quote at least three hours before bid time.  Thanks! 

 

Scope: The work consists of furnishing all labor, materials, equipment, and incidentals necessary to rehabilitate the existing concrete marginal wharf at National City Marine Terminal (NCMT) Berth 24-11 and to reinstall the existing shore power system, as shown on the Contract Drawings and specified herein. The Work includes demolition and removal of portions of the existing concrete deck, pile caps, and appurtenances, construction of a new reinforced concrete deck, repair of existing piles, installation of pile jackets, and replacement of waterfront elements, including bull rails, wale systems, and mooring hardware such as bollards. Electrical work includes removal, relocation, and reinstallation of the existing shore power system and associated infrastructure, including conduits, manholes, and appurtenances, along with complete testing and commissioning of the system as a fully operational installation. The Work also includes installation and replacement of utilities and site improvements, including potable water, stormwater, drainage, pavement replacement, and utility potholing. Additional work includes excavation, backfill, dewatering, demolition, hauling, disposal, and temporary work necessary to complete the Project. The Contractor shall coordinate all work to maintain terminal operations and minimize impacts to tenants and vessel activity.

 

Granite is requesting quotes from all qualified subcontractors and suppliers for ALL bid items.

Plans

Plans, specifications, and addendums are available for viewing at no cost through the following:

Our Office - 2790 Business Park Drive, Vista, CA 92081

PlanetBids Website - https://vendors.planetbids.com/portal/13982/portal-home

Project Website: https://projects.pipelinesuite.com/ehPipelineSubs/dspOpenProject/projectID/367295

 

Other Info

Quotations will be broken down into comparable packages as reasonably necessary.  Granite will work with interested subcontractors to identify opportunities to break down items into economically feasible packages.

 

Please call if you need assistance in obtaining bonding, insurance, equipment, materials, and/or supplies. Granite intends to work cooperatively with all qualified firms seeking work on this project.  Granite is an Equal Opportunity Employer.

 

Requirements:  Granite is signatory to Operating Engineers, Laborers, Teamsters, Cement Masons, and Carpenters Unions.  100% performance and payment bonds required for the full amount of the subcontract price.  Granite may assist with the bond premium up to 1%.  Subcontractors must possess a current contractor’s license, insurance and worker’s compensation insurance coverage meeting Granite’s requirements and will be required to sign the standard Granite Subcontract Agreement.  A copy of the insurance requirements and agreements can be obtained by contacting the Estimator. 

All quotes are subject to the terms of Granite Construction Company’s applicable standard form agreement which is available through the following link:  https://www.graniteconstruction.com/ca-resources/standard-agreements 

 

Subcontractors must also be registered with a current DIR number.  (No bid shall be accepted, nor any subcontract entered into without proof of the Subcontractor’s current registration to perform public work pursuant to Section 1725.5.)  https://www.dir.ca.gov/Public-Works/Contractor-Registration.html

Other Project Contacts

Title Company Estimator Phone Extension Fax Email
Granite Construction Company Jerry Lynch 760-444-1028 805-335-8912 estimating.scr@gcinc.com
Granite Construction Company Diane Deluca 661-571-0860 805-335-8912 diane.deluca@gcinc.com

If you have project-related questions, please contact your contractor or use the "Submit Question" tab.
If you are having technical difficulties downloading, please email support@preconsuite.com or call 949-222-0400.