Project Info
|
| Project # |
26-024 |
|
Project Name
|
GC - New Albany Borough New Wastewater Treatment Facility
|
|
Location
|
New Albany Borough
|
|
Address
|
Map It
401 Main Street
|
|
City
|
New Albany
|
|
State
|
PA
|
|
Zip
|
18833
|
|
Bid Date
|
September 29, 2026
|
|
Bid Time
|
5:00 PM
|
|
|
| Scope |
This project consists of the construction of a new 0.04 mgd package Wastewater Treatment Plant. Including but not limited to; headworks and screen, extended aeration treatment concrete tanks and equipment, UV disinfection, blowers, yard piping, new electrical service, duct banks, new process control and blower building, new headwords building, new U.V Disinfectionbuilding, demolition of existing treatment plant and existing electrical, and all associated appurtenances.
We are requesting bids for the following specification sections:
DIVISION 2 - SITE WORK
- Section 02000: Site Work General Provisions
- Section 02100: Control of Water
- Section 02102: Clearing and Grubbing
- Section 02110: Demolition
- Section 02200: Earthwork
- Section 02205: Earthwork for Pipelines
- Section 02330: Manhole Rehabilitation and Restoration
- Section 02351: Corrugated Polyethylene Pipe
- Section 02541: Erosion and Sediment Control
- Section 02600: Paving, Surfacing, Walkways, and Curbs
- Section 02607: Manholes and Covers
- Section 02610: Sewer Pipe and Appurtenances
- Section 02640: Testing and Disinfecting Water Mains
- Section 02650: Forcemain, Gravity Sewer, and Manhole Testing
- Section 02710: Fencing and Gates
- Section 02733: Televideo Inspection
- Section 02763: Point Repairs and Obstruction Removals
- Section 02820: Topsoil, Seeding and Mulching
DIVISION 3 / 03 - CONCRETE
- Section 03 10 00: Concrete Forming and Accessories
- Section 03 20 00: Concrete Reinforcing
- Section 03 30 00: Cast-In-Place Concrete
- Section 03600: Grout
DIVISION 04 - MASONRY
- Section 04 20 00: Unit Masonry
DIVISION 05 - STRUCTURAL / METALS
- Section 05 12 00: Structural Steel Framing
- Section 05 50 00: Metal Fabrications
- Section 05 52 13: Pipe and Tube Railings
- Section 05 53 13: Bar Gratings
DIVISION 06 - CARPENTRY / WOOD & PLASTICS
- Section 06 10 00: Rough Carpentry
- Section 06 16 00: Sheathing
- Section 06 17 53: Shop-Fabricated Wood Trusses
- Section 06 64 00: Plastic Paneling
DIVISION 07 - WATERPROOFING AND SIDING / THERMAL & MOISTURE PROTECTION
- Section 07 11 13: Bituminous Damproofing
- Section 07 21 00: Thermal Insulation
- Section 07 27 26: Fluid Applied Membrane Air Barriers
- Section 07 31 13: Asphalt Shingles
- Section 07 42 13.13: Formed Metal Wall Panels
- Section 07 42 93: Soffit Panels
- Section 07 46 33: Plastic Siding
- Section 07 71 00: Roof Specialties
- Section 07 72 00: Roof Accessories
- Section 07 92 00: Joint Sealants
DIVISION 08 - BUILDING HARDWARE / OPENINGS
- Section 08 11 13: Hollow Metal Doors and Frames
- Section 08 54 50: Composite Windows
- Section 08 71 00: Door Hardware
- Section 08 91 19: Fixed Louvers
DIVISION 09 - PAINTING / FINISHES
- Section 09 29 00: Gypsum Board
- Section 09 67 23: Resinous Flooring
- Section 09 91 24: Interior Painting (MPI Standards)
DIVISION 10 - ACCESSORIES / SPECIALTIES
- Section 10 14 23: Panel Signage
- Section 10 28 00: Toilet, Bath, and Laundry Accessories
DIVISION 11 - EQUIPMENT
- Section 11000: Equipment General Provisions
- Section 11309: Residential Sewage Ejector System
- Section 11310: Submersible Pump Stations
- Section 11311: Ultraviolet Disinfection Equipment and Backup Chlorination System
- Section 11313: Utility Water System
- Section 11330: Spiral Screen
- Section 11375: Extended Aeration Treatment Plant
DIVISION 12 - LABORATORY / FURNISHINGS
- Section 12 35 53.13: Metal Laboratory Casework
- Section 12 36 61.16: Solid Surface Countertops
DIVISION 15 - MECHANICAL
- Section 15010: Piping Systems General Provisions
- Section 15012: Stainless Steel Pipe
- Section 15020: Copper Pipe
- Section 15040: Valves General Provisions
- Section 15048: PVC/CPVC Valves
- Section 15049: Miscellaneous Valves and Piping Specialties
- Section 15070: Piping System Appurtenances
DIVISION 22 - PLUMBING
- Section 22 05 00: Common Work Results for Plumbing
- Section 22 05 23: General-Duty Valves for Pumping Piping
- Section 22 07 19: Plumbing Piping Insulation
- Section 22 11 16: Domestic Water Piping
- Section 22 13 19.13: Sanitary Drains
- Section 22 33 00: Electric, Domestic Water Heaters
- Section 22 42 00: Commercial Plumbing Fixtures
- Section 22 45 00: Emergency Plumbing Fixtures
DIVISION 23 - HVAC
- Section 23 05 00: Common Work Results for HVAC
- Section 23 23 00: Refrigerant Piping
- Section 23 34 00: HVAC Fans
- Section 23 51 13.16: Vent Dampers
- Section 23 81 26: Split-System Air Conditioner
- Section 23 82 39.19: Wall and Ceiling Unit Heaters
DIVISION 26 - ELECTRICAL
- Section 26 05 00: Common Results for Electrical
- Section 26 05 19: Low Voltage Electrical Power Conductors and Cables
- Section 26 05 26: Grounding and Bonding for Electrical Systems
- Section 26 05 33.13: Conduit for Electrical Systems
- Section 26 05 33.16: Boxes for Electrical Systems
- Section 26 22 00: Dry Type Transformers
- Section 26 23 13: Engine Driven Generator Sets – Diesel
- Section 26 24 16: Panelboards
- Section 26 27 26: Wiring Devices
- Section 26 28 16: Enclosed Switches and Circuit Breakers
- Section 26 36 00: Automatic Transfer Switches
- Section 26 51 00: Building Lighting
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
- Section 28 30 00: Alarm Monitoring System
DIVISION 33 - UTILITIES
- Section 33 30 00: Refrigerated Sampler
|
| Plans |
|
| Other Info |
|
|